As well we all know, implementing enterprise software can get complicated very quickly. Who’s responsible for this again? When were we supposed to have that completed? Is anyone ever going to respond to my emails?! It can get stressful 😤. This page is designed to cut through the fog and give all parties a high-level view of what to expect throughout the course of your a CloudCard implementation.
Timeline
Phase | Action/Project | Description |
---|
Who’s Responsible
Pre-implementation |
Placement in the Implementation |
CloudCard has |
CloudCard
All
Pre-implementation
Organization Settings Questionnaire
unlimited spots available in the Implementation queue. Once we receive a PO, we will place you in the last slot of the queue. Your position in the queue dictates the priority of you implementation to CloudCard. Please view the Implementation Queue page for more information. | ||
Pre-implementation | After we receive the purchase order, we will send you the organization settings questionnaire. It’s designed to help us customize the application to your specific needs. Send it back once you’re finished, and we’ll get right to work! |
VAR/ Customer
All
Pre-implementation |
Integration Questionnaire
If you |
purchased any integration, we will send you the integration questionnaire. This document is designed to answer three major questions:
|
VAR/ Customer
Kick-Off ( |
official start of |
implementation) | Schedule the Kick-off Meeting | This is the official start of the implementation. |
This meeting is designed to clarify any information on the Organization Settings Questionnaire or the Pre-Integration Questionnaire. Additionally, we will identify the projects we expect to complete as part of the implementation. |
VAR
Both questionnaires must be filled out before scheduling a Kick-Off Call. | ||
Organizations will work with CloudCard on any/all/none of the following integration projects depending on the plan and add-ons purchased. | ||
Implementation | General Configuration | Custom logo, colors, emails, settings, ect |
VAR
All
Implementation
Training & Support (Ongoing)
. |
VAR
Implementation | Automates the Bulk Import through a csv scheduled program. |
CloudCard
Implementation | Automates the addition of photos to the database or file system. |
CloudCard
Implementation | Integrates CloudCard with the customer’s single sign-on server, which allows their users to log into CloudCard using their organizational username and password. The SSO Connector can also provision new Online Photo Submission accounts if necessary. |
CloudCard
Implementation | Custom URL (http://photos. |
com) | Allows an organization to configure Online Photo Submission to use their custom domain. |
CloudCard
A+
Implementation | Custom From Address | Allows an organization to send emails from a custom email address using DKIM records. |
CloudCard
The above timeline begins once we have received a purchase order. All of the projects included in the implementation phase are optional . There because there are plenty of instances where times when some projects do not make sense for a customer. If a VAR is not involved in the implementation, CloudCard will assume responsibility for their projects.
Status Meetings
CloudCard will schedule 1-hour, bi-weekly, status meetings that will run throughout the course of the implementation. This is the customer's opportunity to discuss questions arising from projects that CloudCard is responsible for. If customers have questions about projects assigned to our VAR’s, please reach out to them separately. Status meetings can/will be canceled if there are no questions or roadblocks.
Implementation Time
Preparation: 0-2 weeks
Organization Settings Questionnaire (1 hr)
Pre-Integration Questionnaire (1 hr)
Attend Kick-Off Call (1 hr)
Implementation: 2-4 weeks
General Configuration - settings, logo, colors, emails, ect. (5+ min)
CSV Importer (1 hr)
SSO Integration (1 hr)
Photo Downloader (1-3 hr)
Custom URL (5+ min)
Custom From Address (5+ min)
Training: 0-1 weeks
Attend 1 hour CloudCard Online Photo Submission training session